Jean McClung Middle School

Under Construction

DeSoto Athletics

Project overview

This Project is in the Construction Administration phase.

Scope of Work:

This project includes renovations and site improvements to multiple sport fields & facilities

Program Initiatives Addressed:

  • Baseball Field & Softball Field- New Turf & Striping, New base plates, and New Field Logos
  • Tennis Court – Resurfacing existing courts
  • McCowan MS Track- New Track Surface & Striping
  • West MS Track – New Track Surface & Striping
  • Multi-Purpose Practice Field – New Turf and Striping and New Field Logos
  • Indoor Practice Facility- New Turf
Renovations

Updates

September 24, 2026
Asphalt Installation Completed at McCowan MS Track

Hellas has completed the asphalt installation at the McCowan MS track.

No items found.
September 11, 2026
Baseball & Softball Field Improvements Progress

Moisture conditioning has been completed at the high school baseball and softball fields.

No items found.
August 25, 2026
Baseball and Softball Field Improvements Underway

Hellas Construction has mobilized the DeSoto High School baseball and softball fields and has started demolition and excavation activities in preparation for soil stabilization.

No items found.
August 17, 2026
McCowan Middle School Track Replacement Underway

Hellas Construction has completed the demolition of the existing track surface at McCowan Middle School and has begun soil stabilization activities to prepare the subgrade for the new track installation.

No items found.
August 11, 2026
Tennis Court Improvements Complete

Hellas Construction has completed the resurfacing of the DeSoto High School tennis courts, enhancing both the playability and appearance of the facility. The completed improvements provide student-athletes with a refreshed environment for practice and competition.

No items found.
July 17, 2026
Indoor Practice Facility Turf Installation Complete

Hellas Construction has successfully completed the installation of new synthetic turf at the Indoor Practice Facility. Delivering a modernized training surface designed to enhance student-athlete performance and year-round use.

No items found.
June 25, 2026
Groundbreaking of Athletic Projects

DeSoto ISD, PROCEDEO, Hellas Construction, students, and community members gathered to commemorate the groundbreaking of the district's athletic field improvements, officially launching construction under the 2025 Bond Program. The event celebrated the start of the tennis and indoor practice facility improvements, representing the first phase of the district's planned athletic enhancements.

No items found.
June 10, 2026
Indoor Practice Facility: Under Construction

The DeSoto High School Indoor Practice Facility is now under construction. The demolition of the existing turf is complete. The project scope includes new turf and striping.

No items found.