Program Schedule

Design and construction timeline for every 2025 Bond campus, by quarter. Bars show the design and construction phases.

School
2026
Q1
Q2
Q3
Q4
2027
Q1
Q2
Q3
Q4
2028
Q1
Q2
Q3
Q4
2029
Q1
Q2
Q3
Q4
Amber Terrace Early Childhood Learning Center
Q1 2027
Q1 2028
Q1 2027
Q1 2028
In Design
Cockrell Hill Elementary
Q1 2027
Q1 2028
Q1 2027
Q1 2028
In Design
DeSoto West Middle School
Q1 2027
Q2 2028
Q1 2027
Q2 2028
In Design
Frank D. Moates Elementary
Q1 2027
Q2 2029
Q1 2027
Q2 2029
In Design
The Meadows Elementary
Q1 2027
Q1 2028
Q1 2027
Q1 2028
In Design
Woodridge Fine Arts and Gifted Academy
Q1 2027
Q1 2028
Q1 2027
Q1 2028
In Design
DeSoto Athletics
Q2 2026
Q1 2027
Q2 2026
Q1 2027
Under Construction
Administration and Support Facilities
Q2 2027
Q2 2028
Q2 2027
Q2 2028
In Design
Curtistene S. McCowan Middle School
Q2 2027
Q2 2028
Q2 2027
Q2 2028
In Design
DeSoto High School
Q2 2027
Q1 2029
Q2 2027
Q1 2029
In Design
DeSoto High School Stadium
Q2 2027
Q3 2028
Q2 2027
Q3 2028
In Design
Katherine Johnson Technology Magnet Academy
Q2 2027
Q1 2028
Q2 2027
Q1 2028
In Design
DeSoto High School Success Center
Q3 2027
Q2 2029
Q3 2027
Q2 2029
In Design